الثلاثاء، 5 سبتمبر 2023

العلاقة بين نسبة إنجاز المشروع ونسب انتهاء الأنشطة وكيف يتم تحميل الموارد المناسب

 Project Progress% vs Activity % Complete

In order to get the overall percentage of a project, this needs to roll up the activities’ percentage complete. Therefore, we need first to know how to calculate the types of Activity % complete using one of the following rules of credit wherever appropriate:

1-      Quantity or Units Completed​ (Fit for Construction activities)

2-      Incremental Milestone​ (Fit for Engineering and procurement)

3-      Subjective Judgment (Not preferred unless no other option)

4-      Weighted or Equivalent Units Completed​

5-      Resource Expenditure (Level of Effort)​

Subsequently, we apply this on Primavera P6 using one of the following types of Activity % complete:

1-      Duration% (Default, automatically reflecting in EV and Remaining Duration)

2-      Physical% (Reflecting in EV, but Remaining duration should be manually defined)

3-      Units% (For resource-driven schedules, Resource Expenditure or Level of Effort)


To aggregate the overall percentage, the relative weight of each activity should be defined. There are different approaches to do so as follows:

1-      Activity Duration (duration not always reflect the effort required)

2-      Activity Cost (depending on maturity level if they link payments with progress or not)

3-      Activity Manhours/Resources (preferred in construction as it reflects the relative effort)

4-      No. of activities (can be helpful for similar types of submissions with similar effort required to prepare each of them)

5-      Expert Judgement (Not preferred unless no other option)

6-      Composite approach (can be helpful for all aggregating all phases such as engineering, procurement and construction with usage for the suitable approach in each of them)


Example of a composite approach:


The weights can be loaded using one of the resource types of P6 which are:

1-      Labor resource: In this case the units of weights will affect the total of labor units.

2-      Non-labor (Equipment) resource: DITTO but for machinery. However, some practitioners use it in case of not loading equipment on the schedule.

3-      Material resource: I prefer it because normally we don’t need to know total of materials because they are not in numbers, but in different units.


Accordingly, Primavera calculates the overall percent complete based on earned valued which is called performance percentage in P6 vs the planned percentage which is called schedule% in P6. This doesn’t work unless the programme is cost loaded. Therefore, we sometimes multiply these weights% by $1 million to convert them and load as cost. Furthermore, we should be aware of the earned value calculation (Earned value = Percent complete * Budget cost):


Where BCWP is the Earned Value and BCWS is the Planned Value. Likewise, the same can be calculated in percentages as follows:

1-      Performance% = Total earned value / Total budget cost

2-      Schedule% = Total planned value / Total budget cost


Finally, the schedule variance% can be calculated as well (SV% = Performance% - Schedule%) to determine the status of the schedule whether ahead or behind schedule.








ليست هناك تعليقات:

إرسال تعليق