السؤال الخامس والأربعون من الاسئلة الخمسين في أسس علم التخطيط - أنواع التقارير

•ما هي مستويات التقارير وتفاصيلها؟ هي شبيهة بمستويات WBS وبيانها كالتالي:
• Level 1 – Executive Summary Level (Dashboard, Flash report): overall project plan, progress and current forecast, rate: monthly, quarterly.
• Level 2 – Summary Level (Client presentation): Status reports include selected activities/major trades which are extracted from the overall Level 2 Master Programme, rate: monthly, fortnightly.
• Level 3 – Management Level: represent the work sequence and programme, in detail sufficient to plan and monitor weekly activities at the contractor working level, ‘look ahead programmes’, rate: weekly, biweekly contains cumulative.

• Level 4 – Site Level (Daily): the daily progress lists or tick-sheets, which are developed and maintained by each department, section or trade.